Howard Street Construction in Boone: What's Changing Downtown

The asphalt on Howard Street is finished. The Downtown Boone update for the week of October 5 reported that the last stretch of paving was complete and that New River Light and Power had moved all of its services into the new underground duct bank. Look down the street behind King Street now and you see smooth blacktop, new brick and new curbs, with the old wooden utility poles still standing among them.

Those poles show where the project actually stands. Striping, streetlights and wire removal are still ahead, and those are the jobs that change how downtown Boone gets used. Howard Street was built as the back side of King Street. Once those last layers are in, it becomes a second front.

Where the work stands in mid-October

The Downtown Boone construction updates are the most reliable record. Over the past three months they show a clear order of work.

Date of update What it reported
July 6, 2026 Town Hall and King Street parking lots to connect to the new roadway. Howard running two-way for now to keep lot access open
August 10, 2026 Appalachian Street to Depot Street reopened as a one-way road
September 28, 2026 Burrell Street milled and set for paving. Final asphalt lift nearly complete
October 5, 2026 Final paving complete. New River Light and Power services moved underground. Streetlight poles and striping next

The October 5 update lists what comes next. Freedom ElecTech planned to begin setting the new streetlight poles, working from Appalachian Street toward Burrell Street. A few of the smaller poles can go in by hand. The larger 28-foot poles need equipment. A striping crew was expected back near the end of that week to mark the roadway, bike lanes and crosswalks, with some short closures while the work happens.

No completion date has been published, and no ribbon cutting has been announced.

Why the old poles are still up

The poles get a lot of questions, and the August 10 update explained why they remain. The underground system is built, but each utility provider still has to move its own service off the old poles and onto the new lines. The poles don't belong to the Town, and the individual utilities will take them down.

New River Light and Power has now finished its part of that handoff. Its next step is removing its overhead wires, and as of October 5 that work had no schedule.

This is why the end of the project is so hard to date. Paving, striping and lighting are scheduled by the Town and its contractors. Taking down the last wires is up to the utilities. Expect the street to look finished at ground level for a while before the sky above it is clear.

The original plan helps explain the pace. When the Town advertised the project, it estimated about 450 days of construction. Work began Monday, April 21, 2025, with the Howard and Depot intersection closed, so 450 days would have run to about mid-July 2026. The utility moves are a big reason the final months have taken longer than that. The Watauga Democrat put utility delays in the headline of its report when the project was about 75% complete.

How driving downtown changes

The finished design runs about 1,500 linear feet and makes Howard Street a one-way road. The stretch between Appalachian Street and Depot Street has worked that way since August. The Town asked drivers to take extra care with the new signs after months of shifting construction patterns and temporary two-way traffic.

On direction, the planning documents are older than the construction. A traffic study reported by the Watauga Democrat during the 2015 planning stage backed a westbound route, starting at Appalachian Street and running through Depot Street toward Water Street. That was the plan then. The posted signs on the street are the rule now.

For drivers, three changes matter most:

  1. The municipal lots get a back exit. The July 6 update said the Town Hall and King Street parking lots would connect to the new roadway, so drivers can leave straight onto Howard Street. That gives cars leaving those lots a way out that doesn't run along King Street.
  2. Howard becomes a one-way street with a bike lane. The design includes a dedicated bike lane and a pedestrian path alongside the travel lane. Those lanes will only be visible after the striping crew finishes.
  3. Parking advice holds until the work is done. During construction, Downtown Boone has pointed visitors to King Street meters and the King Street, Depot Street and Queen Street lots. The original bid notice mentioned on-street parking and "some additional parking" on Howard. No net count of spaces gained or lost has been published.

How walking downtown changes

The parts of the project people will notice on foot are mostly brick and light. The project overview lists widened sidewalks, ADA-accessible crossings, new street lighting, more than 8,500 square feet of brick hardscape, planting and landscaping, and tree grates and guards. In mid-September, The Appalachian reported the sidewalks and bike lanes as 95% complete, citing the Town's September 7 update.

That finished hardscape still needs crosswalk paint and streetlights before it works fully as a walking route after dark. Those are exactly the two jobs the October 5 update put next in line. The work zone includes some well-known downtown landmarks. The Watauga Democrat described the active section as running between the Appalachian Theatre and Appalachian Street. The August crews worked from the Depot Street side toward The Hope Center.

Businesses tucked behind King Street have been part of the story the whole time. Espresso News sits between buildings behind King Street, and the Watauga Democrat profiled owner Uijin Park keeping the shop open through the construction. Places like it are the ones that gain the most when the street behind them becomes a lit, walkable route instead of a service lane.

What's under the new street

Most of the money went where no one will see it. The overview lists about 1,500 feet of water main, 1,200 feet of sewer upgrades, nearly 1,400 feet of stormwater pipe with 36 inlets and manholes, moving overhead utilities underground, and conduit for future EV chargers. The EV conduit means charging stations can be added later without digging up the new brick.

The project has taken more than a decade. Design approval came in October 2015, and all needed easements were in place by June 2023. The first round of bidding in August 2024 drew no bids, so the Town advertised it again. The Watauga Democrat reported that the Town Council tentatively awarded the construction contract to M&M Construction of Banner Elk for $12,293,118. At the time of the award, the paper put the total project cost at $15,961,703. The funding included a $9,737,180 USDA loan, a $300,000 Appalachian Regional Commission grant and a $1,388,281 state grant. Those were the figures at the contract award. Later grant reporting has not been fully matched against them.

When to see it for yourself

The next downtown evenings on the calendar are the First Friday Art Crawls on November 6 and December 4, both from 5:00 to 8:00 p.m. The event listings don't place the crawl on Howard Street. Still, if the striping and lighting stay on schedule, either evening is a good chance to park in a municipal lot and try the new exit, or to walk back from King Street along the new brick. Downtown Boone takes project questions at 828-268-6283 and posts weekly updates on its Howard Street page.

Downtown projects like Howard Street change how a block gets used long before the last pole comes down. If you're thinking about what that means for a property near King Street, or anywhere in Boone, Robin Lineberger Stykes can walk you through the details step by step. Schedule a consultation whenever you're ready.